The Sharyland Water Supply Corporation Reservoir is an ongoing project.
The project involves constructing an earthen reservoir with concrete sloped paving on the inside slopes of the reservoir. This reservoir is approximately 1,200 feet long by 650 feet wide. We will have to place over 200,000 cubic yards of earthen material and compact it to a 95% density based off of a modified proctor.
We use the latest in GPS surveying and machine controls to insure that we are only handling the dirt one time. This has enabled us to provide very accurate pay requests and an exact accounting of how much material we have placed within a given time.