The El Pico Water Treatment Plant project consists of constructing a new 20 million gallon per day water treatment plant that is being built for the city of Laredo at an estimated cost of $89 million.
Our primary scope on the project is to construct the Raw Water Pump Station and the River Intake Structure. The Raw Water Pump Station is a concrete structure that is approximately 60 feet tall. The River Intake Structure will be built right on the bank of the Rio Grande River.
This project is scheduled to be completed within 18 months from the start date. Foremost Paving and Western Summit, a Kiewit Company, are joint venture partners on this project.